ATB data for geothermal are shown above. These projections use bottom-up models derived from the analysis and results of the GeoVision: Harnessing the Heat Beneath our Feet report (DOE, 2019). The GeoVision report is a collaborative multiyear effort with contributors from industry, academia, national laboratories, and federal agencies. The analysis in the report updates resource potential estimates as well as current and projected capital and O&M costs through evaluation of current industry trends and predicted advancements in areas such as drilling efficiency and materials and enhanced geothermal system (EGS) stimulation success. Drilling and EGS improvements enable reduced development timelines, CAPEX, and financing rates.
The three scenarios for technology innovation are:
Within the 2020 ATB, geothermal resources broadly consist of two main types: hydrothermal and enhanced geothermal systems (EGS). Hydrothermal systems are naturally occurring zones of Earth-heated circulating fluid that can be exploited for electricity generation if certain minimum temperatures and flow rates are achieved for a given power plant technology. EGS exhibit naturally occurring zones of heat but lack sufficient fluid flow and require engineering to enhance permeability. These are then subdivided based on site specific resource characteristics and compatible power plant technology.
The two types of energy conversion processes used to generate geothermal electricity are: binary organic Rankine cycle and flash.
The ATB defines flash resources as those with temperatures at or above 200°C and binary resources as those with temperatures between 110 to <200°C. EGS resources are further subdivided into near-hydrothermal field EGS (NF-EGS) and deep EGS. The resultant geothermal resource supply curves (~139,000 MW) consist of six categories: hydrothermal flash, hydrothermal binary, NF-EGS flash, NF-EGS binary, deep EGS flash, and deep EGS binary. For illustration in the ATB, six representative geothermal plants are shown with design parameters based on each respective resource category.
Examples using these plant types in each of the three resource categories (hydrothermal, NF-EGS, and deep EGS) are shown in the ATB.
Temp (°C) | >=200C | 150–200 | 135–150 | <135 | |
Hydrothermal | Number of identified sites | 21 | 23 | 17 | 59 |
Total capacity (MW) | 15,338 | 2,991 | 820 | 4,632 | |
Average OCC ($/kW) | 4,175 | 8,829 | 9,476 | 17,757 | |
Min OCC ($/kW) | 3,000 | 4,397 | 7,444 | 11,884 | |
Max OCC ($/kW) | 5,971 | 38,720 | 11,781 | 25,934 | |
Example of plant OCC ($/kW) | 4,522 | 5,870 | n/a | ||
NF-EGS | Number of sites | 12 | 20 | ||
Total capacity (MW) | 787 | 596 | |||
Average OCC ($/kW) | 11,429 | 27,330 | |||
Min OCC ($/kW) | 9,026 | 18,974 | |||
Max OCC ($/kW) | 18,797 | 41,694 | |||
Example of plant OCC ($/kW) | 14,486 | 32,921 | |||
Deep EGS (3–6 km) | Number of sites | n/a | n/a | n/a | |
Total capacity (MW) | 100,000+ | ||||
Average OCC ($/kW) | 28,991 | 65,081 | |||
Min OCC ($/kW) | 18,733 | 40,515 | |||
Max OCC ($/kW) | 54,987 | 96,405 | |||
Example of plant OCC ($/kW) | 14,486 | 32,921 |
The hydrothermal geothermal resource potential is concentrated in the western United States. The total mean potential estimated by the U.S. Geological Survey (USGS) in 2008 is 39,090 MW: 9,057 MW identified and 30,033 MW undiscovered (USGS, 2008)(USGS, 2008). The resource potential identified at each site is based on available reservoir thermal energy information from studies conducted at the site (USGS, 2008). The undiscovered hydrothermal resource estimate is based on a series of geographic information system (GIS) statistical models of the spatial correlation of geological factors that facilitate the formation of geothermal systems.
The USGS resource potential estimates for hydrothermal are used with the following modifications:
The EGS resource potential is concentrated in the western United States, but technology innovations as described in the Advanced Scenario would increase potential beyond the western US. The total potential is greater than 100,000 MW: 1,493 MW of NF-EGS and the remainder from deep EGS. The NF-EGS resource potential is based on data from USGS for EGS potential on the periphery of select identified hydrothermal sites (Augustine, et al., 2019). The deep EGS resource potential (Roberts, 2009; Augustine, 2016) is based on Sothern Methodist University Geothermal Laboratory temperature-at-depth maps and the methodology is from Tester et al., 2006.
Scenario | Drilling Advancements | EGS Development |
Conservative | Technology Description: Drilling efficiency improvements (e.g., utilizing mechanical specific energy with PDC bits and limiting bit disfunction leads to longer bit life) result in minor decreases in drilling costs and little to no timeline reduction.
Justification: Substantial increases in drilling rate of penetration (ROP) are unlikely without wider adoption of oil & gas technologies and new bit innovations. | Technology Description: Current well stimulation techniques do not consistently generate adequate economic flow rates of sustained flow from unsuccessful wells leading to little to no improvement of drilling success rate or CAPEX reduction.
Justification: Stimulation is cost prohibitive and lacks zonal isolation. Both the precision and scale of stimulation must improve. |
Moderate | Technology Description: ROP and bit life are doubled along with a reduction in timelines and consumption of drilling materials.
Justification: Cost modeling of drilling improvements along with limited successful field demonstrations and abundant oil and gas experience confirm this level of advancement is achievable (Lowry et al., 2017a and 2017b; Hackett et al., 2020).
| Technology Description: As above, stimulation techniques remain cost prohibitive.
Justification: To remain consistent with the GeoVision Report cost modeling for stimulation technology has yet to be performed for a mid-case scenario. Additionally, successful deployment of EGS technology is modeled as coupled with significant drilling advancements as lower drilling costs and improved directional drilling in hard rock environments will likely help enable EGS reservoir development. |
Advanced | Technology Description: ROP and bit life are increased 4 times over conservative. Wells are constructed as mono-bore using expandable casing. The increased speeds result in significantly shorter timelines and lower consumption of drilling related materials.
Justification: Ongoing ARPA-E, Sandia, NREL, etc. research (e.g., laser drilling and electric pulse) is directed at reducing the cost, style, and duration of well drilling. Growing interest from the oil and gas sector is leading to knowledge transfer. | Technology Description: Both stimulation success rate, control, and sustained flow rate advance to economic levels.
Justification: The ongoing EGS Collab, FORGE project, and other DOE GTO sponsored research are demonstrating stimulation techniques in hard rock environments including hydraulic shearing, zonal isolation, etc. |
Impact | Reductions in drilling capital expenditures and financing costs through shorter development timelines. Development of high-temperature tools and electronics and drill steering technology for geothermal subsurface operations. Reduction in duration from start to commercial operation date. Increased viability of deeper resources due to drilling advancements. | Reductions in well completion (stimulation) capital expenditures. Reduction in perceived project risk resulting in lower financing rates. Development of reservoir engineering techniques and technologies that enable EGS. Increased drilling success rate from stimulation improvements leading to fewer wells drilled and shorter timelines. Expansion of economic resource supply. |
References | (McClure & Horne, 2014) (DOE, 2016) "The Raft River Enhanced Geothermal System Project," Informatics, accessed 2018 "Enhanced Geothermal Systems Demonstration Projects," DOE, accessed 2018 "Frontier Observatory for Research in Geothermal Energy (FORGE)," DOE, accessed 2018 |
Scenario | Rate of Penetration (ft/hr) | Bit Life (hr) | EGS Flow Rate (kg/s) |
Conservative (2018) | 25 | 50 | 40 |
Moderate | 50 | 100 | 40 |
Advanced | 100 | 200 | 80 flash / 110 binary |
Hydrothermal geothermal technologies encompass technologies for exploring for the resource, drilling to access the resource, and building power plants to convert geothermal energy to electricity. Technology costs depend heavily on the hydrothermal resource temperature and well productivity and depth, so much so that project costs are site-specific and applying a "typical" cost to any given site would be inaccurate. The 2020 ATB uses scenarios developed by the DOE Geothermal Technologies Office (Mines, 2013) for representative binary and flash hydrothermal power plant technologies.
The first scenario assumes a 175°C resource at a depth of 1.5 km with wells producing an average of 110 kg/s of geothermal brine supplied to a 30-MWe binary (organic Rankine cycle) power plant. The second scenario assumes a 225°C resource at a depth of 2.5 km with wells producing 80 kg/s of geothermal brine supplied to a 40-MWe dual-flash plant. These are mid-grade or "typical" temperatures and depths for binary and flash hydrothermal projects.
The 2020 ATB representative technologies fall in the middle or near the end of the hydrothermal resources cost estimates typically deployed in Regional Energy Deployment System (ReEDS) model runs.
As with costs for projects that use hydrothermal resources, EGS resource project costs depend so heavily on the hydrothermal resource temperature and well productivity and depth that project costs are site-specific. The 2020 ATB uses scenarios developed by the DOE Geothermal Technologies Office (Mines, 2013) for representative binary and flash EGS power plants assuming current (immature) EGS technology performance metrics. The first scenario assumes a 175°C resource at a depth of 3 km with wells producing an average of 40 kg/s of geothermal brine supplied to a 25-MWe binary (organic Rankine cycle) power plant. The second scenario assumes a 250°C resource at a depth of 3.5 km with wells producing 40 kg/s of geothermal brine supplied to a 30-MWe dual-flash plant. These temperatures and depths are at the low-cost end of the EGS supply curve and would be some of the first developed.
This section describes methodology to develop assumptions for CAPEX, O&M, and capacity factor. Click on these links for standardized assumptions for labor cost, regional cost variation, materials cost index, scale of industry, policies and regulations, and inflation.
The site-specific nature of geothermal plant cost, the relative maturity of hydrothermal plant technology, and the very early stage development of EGS technologies make cost projections difficult. The GeoVision scenarios were based on bottom-up analysis of potential cost and performance improvements. The inputs for these scenarios were developed by the national laboratories as part of the GeoVision effort, and it was reviewed by industry experts.
The cost and performance estimates are calculated using Geothermal Electricity Technology Evaluation Model (GETEM), a bottom-up cost analysis tool that accounts for each phase of development of a geothermal plant (DOE "Geothermal Electricity Technology Evaluation Model").
Definition: For the ATB—and based on EIA (2016) and GETEM component cost calculations—the geothermal plant envelope is defined to include:
Regional cost variations and geographically specific grid connection costs are not included in the ATB (CapRegMult = 1; GCC = 0).
In the ATB, CAPEX is shown for six representative plants. CAPEX estimates for all hydrothermal NF-EGS potential result in a CAPEX range that is much broader than that shown in the ATB. It is unlikely that all the resource potential will be developed due to the high costs for some sites. Regional cost effects and distance-based spur line costs are not estimated.
CAPEX in the ATB does not represent regional variants (CapRegMult) associated with labor rates, material costs, etc.
CAPEX in the ATB does not include geographically determined spur line (GCC) from plant to transmission grid.
Base Year: GETEM inputs are derived from the Business-as-Usual (BAU) scenario from GeoVision ((DOE, 2019), (Augustine et al., 2019)). Costs are for new or greenfield hydrothermal projects, not for re-drilling or additional development/capacity additions at an existing site. The following chart shows historical CAPEX and LCOE for geothermal.
Future Years: Projection of future geothermal plant CAPEX for three scenarios are derived from modeled costs in the GeoVision Report.
Use the following table to view the components of CAPEX.
Definition: Operations and maintenance (O&M) costs represent average annual fixed expenditures (and depend on rated capacity) required to operate and maintain a hydrothermal plant over its lifetime of 30 years (plant and reservoir), including:
Base Year: GETEM is used to estimate FOM for each of the six representative plants. FOM for NF-EGS and EGS are equivalent.
Future Years: Future FOM cost reductions are based on results from the GeoVision Technology Improvement scenario (DOE, 2019) and are described in detail in Augustine, Ho, and Blair (2019).
Use the following table to view the components of operating expenditures.
Definition: Geothermal plant capacity factor is influenced by diurnal and seasonal air temperature variation (for air-cooled plants), technology (e.g., binary or flash), downtime, and internal plant energy losses.
Estimates of capacity factor for geothermal plants in the ATB represent typical operation.
Base Year: The capacity factor estimates are developed using GETEM at typical design air temperature and based on design plant capacity net losses. An additional reduction is applied to approximate potential variability due to seasonal temperature effects.
Some geothermal plants have experienced year-on-year reductions in energy production, but this is not consistent across all plants. No approximation of long-term degradation of energy output is assumed.
Future Years: Capacity factors remain unchanged from the Base Year through 2050. Technology improvements are focused on CAPEX costs. The dispatch characteristics of these systems can be valuable to the electric system to manage changes in net electricity demand. Actual capacity factors will be influenced by the degree to which system operators call on geothermal plants to manage grid services. However, a constant dispatch profile is modeled in the ATB and no change is assumed over time.
The following references are specific to this page; for all references in this ATB, see References.
Augustine, Chad, Ho, Jonathan, & Blair, Nate. (2019). GeoVision Analysis Supporting Task Force Report: Electric Sector Potential to Penetration. (No. NREL/ TP-6A20-71833). National Renewable Energy Laboratory. https://doi.org/10.2172/1524768
DOE (2016). Geothermal Technical Working Paper No. 4: Hydraulic Stimulation. (No. DOE/EE-1396.4). U.S. Department of Energy Energy Efficiency and Renewable Energy. http://www1.eere.energy.gov/library/asset_handler.aspx?src=https://www1.eere.energy.gov/geothermal/pdfs/twp4_hydraulic_stimulation-public_comments_final_draft.pdf&id=7453
DOE (2019). GeoVision: Harnessing the Heat Beneath Our Feet. (No. DOE/EE–1306). U.S. Department of Energy. https://www.energy.gov/sites/prod/files/2019/06/f63/GeoVision-full-report-opt.pdf
EIA (2015). Annual Energy Outlook 2015 with Projections to 2040. (No. AEO2015). U.S. Energy Information Administration. https://www.eia.gov/outlooks/archive/aeo15/
EIA (2016). Capital Cost Estimates for Utility Scale Electricity Generating Plants. U.S. Energy Information Administration. https://www.eia.gov/analysis/studies/powerplants/capitalcost/pdf/capcost_assumption.pdf
Hackett, Logan, Blankenship, Douglas, & Robertson-Tai, Ann. (2020). Analysis of Drilling Performance Using PDC Bits, Fallon FORGE Well 21-31. Proceedings. https://pangea.stanford.edu/ERE/db/GeoConf/papers/SGW/2020/Hackett.pdf
Jain, Jayesh R., Ricks, Gregory, Baxter, Benjamin, Vempati, Chaitanya, Peters, Volker, Bilen, Juan-Miguel, Spencer, Reed, & Stibbe, Holger. (2016). A Step Change in Drill-Bit Technology with Self-Adjusting Polycrystalline-Diamond-Compact Bits. Society of Petroleum Engineers. https://doi.org/10.2118/178815-MS
Kalinina, Elena A., Hadgu, Teklu, Klise, Katherine A., & Lowry, Thomas S. (2014). Thermal Performance of Directional Wells for EGS Heat Extraction. Proceedings. https://pangea.stanford.edu/ERE/pdf/IGAstandard/SGW/2014/Kalinina.pdf
Li, Tao (2015). Solid Expandable Tubular Patching Technique for High-Temperature and High-Pressure Casing Damaged Wells. Petroleum Exploration and Development, 42(3), 408-413.
Lowry, Thomas S., Finger, John T., Carrigan, Charles R., Foris, Adam, Kennedy, Mack B., Corbet, Thomas F., Doughty, Christine A., & Pye, Stephen. (2017). GeoVision Analysis Supporting Task Force Report: Reservoir Maintenance and Development. (No. SAND2017-9977). Sandia National Laboratories. https://doi.org/10.2172/1394062
Lowry, Thomas S., Foris, Adam, Finger, John T., Pye, Stephen, & Blankenship, Douglas A. (2017). Implications of Drilling Technology Improvements on the Availability of Exploitable EGS Resources. Proceedings. https://pangea.stanford.edu/ERE/pdf/IGAstandard/SGW/2017/Lowry.pdf
Lukawski, Maciej Z., Anderson, Brian J., Chad, Augustine, Capuano, Louis E., Beckers, Koenraad F., Livesay, Bill, & Tester, Jefferson W. (2014). Cost Analysis of Oil, Gas, and Geothermal Well Drilling. Journal of Petroleum Science and Engineering, 118, 1-14.
McClure, Mark W., & Horne, Roland N. (2014). An Investigation of Stimulation Mechanisms in Enhanced Geothermal Systems. International Journal of Rock Mechanics and Mining Sciences, 27, 242-260.
Mines, Greg (2013). Geothermal Electricity Technology Evaluation Model (GETEM). https://energy.gov/sites/prod/files/2014/02/f7/mines_getem_peer2013.pdf
Teodoriu, Catalin (2015). Dynamic Casing Shoe While Drilling: A Smart Drilling Concept for Future Monobore Technologies. Journal of Natural Gas Science and Engineering, 27(3), 1279-1286.
USGS (2008). Assessment of Moderate- and High-Temperature Geothermal Resources of the United States. (No. Fact Sheet 2008-3082). U.S. Geological Survey. https://pubs.usgs.gov/fs/2008/3082/pdf/fs2008-3082.pdf
Developed with funding from the U.S. Department of Energy’s Office of Energy Efficiency and Renewable Energy.