The table and figures below summarize current (2016) and projected (2030, 2050) technology cost and performance from the 2017 ATB data spreadsheet by generation technology and year, including CF (capacity factor) range, CAPEX (capital expenditure) range, fuel cost, O&M (operations and maintenance) cost (fixed and variable), and calculated levelized cost of energy (LCOE) range.
Levelized cost of energy (LCOE) is a simple metric that combines the primary technology cost and performance parameters: CAPEX, O&M, and CF. It is included in the ATB for illustrative purposes. The ATB focuses on defining the primary cost and performance parameters for use in electric sector modeling or other analysis where more sophisticated comparisons among technologies are made. The LCOE accounts for the energy component of electric system planning and operation. The LCOE uses an annual average capacity factor when spreading costs over the anticipated energy generation. This annual capacity factor ignores specific operating behavior such as ramping, start-up, and shutdown that could be relevant for more detailed evaluations of generator cost and value. Electricity generation technologies have different capabilities to provide such services. For example, wind and PV are primarily energy service providers while the other electricity generation technologies provide capacity and flexibility services in addition to energy. These capacity and flexibility services are difficult to value and depend strongly on the system in which a new generation plant is introduced. These services are represented in electric sector models such as the ReEDS model and corresponding analysis results such as the Standard Scenarios.
To estimate LCOE, assumptions about the cost of capital to finance electricity generation projects are required, and the LCOE calculations are sensitive to these financial assumptions. Three project finance structures are used within the ATB:
These parameters are allowed to vary by year. Effects of the PV import tariffs are represented, as are the recent changes to Modified Accelerated Cost Recovery System (MACRS) and corporate tax rates. The equations and variables used to estimate LCOE are defined on the equations and variables page. For illustration of the impact of changing financial structures such as WACC, see Project Finance Impact on LCOE.
For the renewable electricity generation technologies, Constant, Mid, and Low technology cost scenarios appearing in the table and figures refer to a range of perspectives based on publicly available literature. These three technology advance scenarios are generally described as follows:
For conventional technologies, Constant, Mid, and Low technology cost designations appearing in the tables and figures refer to a range of fuel price projections derived from AEO 2017.
The following technology abbreviations are shown:
CF Range | CAPEX Range | OPEX | LCOE Range | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Technology | Min. (%) | Max. (%) | Min. ($/kW) | Max. ($/kW) | Fuel Costs ($/MWh) | Fixed O&M ($/kW-yr) | Variable O&M ($/MWh) |
Min. ($/MWh) | Max. ($/MWh) |
|
Dispatchable | ||||||||||
Coal | PC | 53% | 85% | $ 3,952 | $ 3,952 | $ 19 | $ 33 | $ 5 | $ 72 | $ 100 |
IGCC | 53% | 85% | $ 4,241 | $ 4,241 | $ 19 | $ 54 | $ 8 | $ 80 | $ 112 | |
CCS-30% | 53% | 85% | $ 5,470 | $ 5,470 | $ 21 | $ 69 | $ 7 | $ 98 | $ 139 | |
CCS-90% | 53% | 85% | $ 6,049 | $ 6,049 | $ 25 | $ 80 | $ 10 | $ 112 | $ 158 | |
Natural Gas | CT | 8% | 30% | $ 902 | $ 902 | $ 28 | $ 12 | $ 7 | $ 59 | $ 120 |
CC | 56% | 87% | $ 1,054 | $ 1,054 | $ 19 | $ 10 | $ 3 | $ 30 | $ 35 | |
CC-CCS | 56% | 87% | $ 2,201 | $ 2,201 | $ 22 | $ 33 | $ 7 | $ 49 | $ 60 | |
Nuclear | 92% | 92% | $ 6,158 | $ 6,158 | $ 7 | $ 99 | $ 2 | $ 63 | $ 63 | |
Biopower | 56% | 56% | $ 3,970 | $ 4,100 | $ 39 | $ 53 | $ 5 | $ 107 | $ 109 | |
Geothermal | 80% | 90% | $ 5,127 | $13,673 | $ 0 | $ 145 | $ 317 | $ 82 | $ 237 | |
CSP with 10-hr TES | 44% | 60% | $ 7,872 | $ 7,872 | $ 0 | $ 67 | $ 4 | $ 123 | $ 167 | |
Non-Dispatchable | ||||||||||
Wind | Land-based | 11% | 48% | $ 1,529 | $ 1,751 | $ 0 | $ 51 | $ 0 | $ 37 | $ 169 |
Offshore | 31% | 51% | $ 3,800 | $ 8,204 | $ 0 | $ 131 | $ 0 | $ 104 | $ 268 | |
Photovoltaic | Utility | 15% | 27% | $ 1,778 | $ 1,778 | $ 0 | $ 14 | $ 0 | $ 45 | $ 81 |
Commercial | 12% | 20% | $ 2,597 | $ 2,597 | $ 0 | $ 18 | $ 0 | $ 88 | $ 145 | |
Residential | 13% | 21% | $ 3,782 | $ 3,782 | $ 0 | $ 23 | $ 0 | $ 119 | $ 197 | |
Hydropower | 60% | 66% | $ 3,971 | $ 7,412 | $ 0 | $ 41 | $ 0 | $ 36 | $ 70 |
CF Range | CAPEX Range | OPEX | LCOE Range | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Technology | Min. (%) | Max. (%) | Min. ($/kW) | Max. ($/kW) | Fuel Costs ($/MWh) | Fixed O&M ($/kW-yr) | Variable O&M ($/MWh) |
Min. ($/MWh) | Max. ($/MWh) |
|
Dispatchable | ||||||||||
Coal | PC | 53% | 85% | $ 3,802 | $ 3,802 | $ 20 | $ 33 | $ 5 | $ 71 | $ 98 |
IGCC | 53% | 85% | $ 3,954 | $ 3,954 | $ 17 | $ 54 | $ 8 | $ 75 | $ 105 | |
CCS-30% | 53% | 85% | $ 5,172 | $ 5,172 | $ 21 | $ 69 | $ 7 | $ 94 | $ 134 | |
CCS-90% | 53% | 85% | $ 5,720 | $ 5,720 | $ 21 | $ 80 | $ 10 | $ 104 | $ 148 | |
Natural Gas | CT | 8% | 30% | $ 852 | $ 852 | $ 41 | $ 12 | $ 7 | $ 71 | $ 129 |
CC | 56% | 87% | $ 1,001 | $ 1,001 | $ 28 | $ 10 | $ 3 | $ 40 | $ 45 | |
CC-CCS | 56% | 87% | $ 1,991 | $ 1,991 | $ 34 | $ 33 | $ 7 | $ 60 | $ 70 | |
Nuclear | 92% | 92% | $ 5,887 | $ 5,887 | $ 7 | $ 99 | $ 2 | $ 61 | $ 61 | |
Biopower | 56% | 56% | $ 3,733 | $ 3,956 | $ 39 | $ 51 | $ 5 | $ 104 | $ 107 | |
Geothermal | 80% | 90% | $ 4,948 | $13,195 | $ 0 | $ 145 | $ 317 | $ 80 | $ 230 | |
CSP with 10-hr TES | 44% | 60% | $ 5,806 | $ 5,806 | $ 0 | $ 50 | $ 4 | $ 90 | $ 122 | |
Non-Dispatchable | ||||||||||
Wind | Land-based | 16% | 51% | $ 1,304 | $ 2,054 | $ 0 | $ 47 | $ 0 | $ 29 | $ 132 |
Offshore | 33% | 52% | $ 2,530 | $ 5,946 | $ 0 | $ 127 | $ 0 | $ 66 | $ 164 | |
Photovoltaic | Utility | 15% | 27% | $ 821 | $ 821 | $ 0 | $ 7 | $ 0 | $ 20 | $ 36 |
Commercial | 12% | 20% | $ 1,111 | $ 1,111 | $ 0 | $ 8 | $ 0 | $ 36 | $ 60 | |
Residential | 13% | 21% | $ 1,493 | $ 1,493 | $ 0 | $ 9 | $ 0 | $ 45 | $ 74 | |
Hydropower | 60% | 66% | $ 3,971 | $ 7,132 | $ 0 | $ 41 | $ 0 | $ 36 | $ 69 |
CF Range | CAPEX Range | OPEX | LCOE Range | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Technology | Min. (%) | Max. (%) | Min. ($/kW) | Max. ($/kW) | Fuel Costs ($/MWh) | Fixed O&M ($/kW-yr) | Variable O&M ($/MWh) |
Min. ($/MWh) | Max. ($/MWh) |
|
Dispatchable | ||||||||||
Coal | PC | 53% | 85% | $ 3,578 | $ 3,952 | $ 19 | $ 33 | $ 5 | $ 72 | $ 100 |
IGCC | 53% | 85% | $ 3,575 | $ 4,241 | $ 19 | $ 54 | $ 8 | $ 80 | $ 112 | |
CCS-30% | 53% | 85% | $ 4,655 | $ 5,470 | $ 21 | $ 69 | $ 7 | $ 98 | $ 139 | |
CCS-90% | 53% | 85% | $ 5,148 | $ 6,049 | $ 25 | $ 80 | $ 10 | $ 112 | $ 158 | |
Natural Gas | CT | 8% | 30% | $ 786 | $ 786 | $ 28 | $ 12 | $ 7 | $ 59 | $ 120 |
CC | 56% | 87% | $ 927 | $ 927 | $ 19 | $ 10 | $ 3 | $ 30 | $ 35 | |
CC-CCS | 56% | 87% | $ 1697 | $ 1697 | $ 22 | $ 33 | $ 7 | $ 49 | $ 60 | |
Nuclear | 92% | 92% | $ 5,211 | $ 5,211 | $ 7 | $ 99 | $ 2 | $ 57 | $ 57 | |
Biopower | 56% | 56% | $ 3,409 | $ 3,742 | $ 39 | $ 51 | $ 5 | $ 101 | $ 103 | |
Geothermal | 80% | 90% | $ 4,692 | $12,511 | $ 0 | $ 145 | $ 317 | $ 77 | $ 220 | |
CSP with 10-hr TES | 44% | 60% | $ 4,645 | $ 4,645 | $ 0 | $ 50 | $ 4 | $ 75 | $ 101 | |
Non-Dispatchable | ||||||||||
Wind | Land-based | 20% | 55% | $ 1,219 | $ 2,290 | $ 0 | $ 39 | $ 0 | $ 25 | $ 111 |
Offshore | 34% | 54% | $ 2,075 | $ 5,123 | $ 0 | $ 122 | $ 0 | $ 54 | $ 130 | |
Photovoltaic | Utility | 15% | 27% | $ 669 | $ 669 | $ 0 | $ 6 | $ 0 | $ 16 | $ 29 |
Commercial | 12% | 20% | $ 954 | $ 954 | $ 0 | $ 7 | $ 0 | $ 31 | $ 51 | |
Residential | 13% | 21% | $ 1,140 | $ 1,140 | $ 0 | $ 7 | $ 0 | $ 34 | $ 56 | |
Hydropower | 60% | 66% | $ 3,971 | $ 6,776 | $ 0 | $ 41 | $ 0 | $ 36 | $ 66 |
CF Range | CAPEX Range | OPEX | LCOE Range | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Technology | Min. (%) | Max. (%) | Min. ($/kW) | Max. ($/kW) | Fuel Costs ($/MWh) | Fixed O&M ($/kW-yr) | Variable O&M ($/MWh) |
Min. ($/MWh) | Max. ($/MWh) |
|
Dispatchable | ||||||||||
Coal | PC | 53% | 85% | $ 3,896 | $ 3,896 | $ 19 | $ 33 | $ 5 | $ 74 | $ 105 |
IGCC | 53% | 85% | $ 4,180 | $ 4,180 | $ 19 | $ 54 | $ 8 | $ 84 | $ 118 | |
CCS-30% | 53% | 85% | $ 5,392 | $ 5,392 | $ 21 | $ 69 | $ 7 | $ 102 | $ 145 | |
CCS-90% | 53% | 85% | $ 5,962 | $ 5,962 | $ 25 | $ 80 | $ 10 | $ 117 | $ 166 | |
Natural Gas | CT | 8% | 30% | $ 898 | $ 898 | $ 28 | $ 12 | $ 7 | $ 59 | $ 122 |
CC | 56% | 87% | $ 1,050 | $ 1,050 | $ 19 | $ 10 | $ 3 | $ 30 | $ 36 | |
CC-CCS | 56% | 87% | $ 2,192 | $ 2,192 | $ 22 | $ 33 | $ 7 | $ 49 | $ 61 | |
Nuclear | 92% | 92% | $ 6,070 | $ 6,070 | $ 7 | $ 99 | $ 2 | $ 63 | $ 63 | |
Biopower | 56% | 56% | $ 3,942 | $ 4,070 | $ 39 | $ 53 | $ 5 | $ 107 | $ 109 | |
Geothermal | 80% | 90% | $ 5,100 | $13,601 | $ 0 | $ 145 | $ 317 | $ 76 | $ 219 | |
CSP with 10-hr TES | 44% | 60% | $ 7,842 | $ 7,842 | $ 0 | $ 67 | $ 4 | $ 95 | $ 128 | |
Non-Dispatchable | ||||||||||
Wind | Land-based | 11% | 48% | $ 1,523 | $ 1,744 | $ 0 | $ 51 | $ 0 | $ 22 | $ 166 |
Offshore | 31% | 51% | $ 3,776 | $ 8,152 | $ 0 | $ 131 | $ 0 | $ 95 | $ 241 | |
Photovoltaic | Utility | 15% | 27% | $ 1,774 | $ 1,774 | $ 0 | $ 14 | $ 0 | $ 35 | $ 63 |
Commercial | 12% | 20% | $ 2,591 | $ 2,591 | $ 0 | $ 18 | $ 0 | $ 69 | $ 113 | |
Residential | 13% | 21% | $ 3,782 | $ 3,782 | $ 0 | $ 23 | $ 0 | $ 92 | $ 153 | |
Hydropower | 60% | 66% | $ 3,956 | $ 7,383 | $ 0 | $ 41 | $ 0 | $ 35 | $ 69 |
CF Range | CAPEX Range | OPEX | LCOE Range | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Technology | Min. (%) | Max. (%) | Min. ($/kW) | Max. ($/kW) | Fuel Costs ($/MWh) | Fixed O&M ($/kW-yr) | Variable O&M ($/MWh) |
Min. ($/MWh) | Max. ($/MWh) |
|
Dispatchable | ||||||||||
Coal | PC | 53% | 85% | $ 3748 | $ 3748 | $ 20 | $ 33 | $ 5 | $ 85 | $ 120 |
IGCC | 53% | 85% | $ 3,898 | $ 3,898 | $ 17 | $ 54 | $ 8 | $ 90 | $ 128 | |
CCS-30% | 53% | 85% | $ 5,099 | $ 5,099 | $ 21 | $ 69 | $ 7 | $ 113 | $ 164 | |
CCS-90% | 53% | 85% | $ 5,638 | $ 5,638 | $ 21 | $ 80 | $ 10 | $ 125 | $ 181 | |
Natural Gas | CT | 8% | 30% | $ 849 | $ 849 | $ 41 | $ 12 | $ 7 | $ 76 | $ 147 |
CC | 56% | 87% | $ 997 | $ 997 | $ 28 | $ 10 | $ 3 | $ 42 | $ 48 | |
CC-CCS | 56% | 87% | $ 1,983 | $ 1,983 | $ 34 | $ 33 | $ 7 | $ 64 | $ 77 | |
Nuclear | 92% | 92% | $ 5,803 | $ 5,803 | $ 7 | $ 99 | $ 2 | $ 72 | $ 72 | |
Biopower | 56% | 56% | $ 3,706 | $ 3,928 | $ 39 | $ 51 | $ 5 | $ 115 | $ 117 | |
Geothermal | 80% | 90% | $ 4,922 | $13,125 | $ 0 | $ 145 | $ 317 | $ 83 | $ 240 | |
CSP with 10-hr TES | 44% | 60% | $ 5,784 | $ 5,784 | $ 0 | $ 50 | $ 4 | $ 88 | $ 119 | |
Non-Dispatchable | ||||||||||
Wind | Land-based | 16% | 51% | $ 1,299 | $ 2,046 | $ 0 | $ 47 | $ 0 | $ 32 | $ 147 |
Offshore | 33% | 52% | $ 2,514 | $ 5,909 | $ 0 | $ 127 | $ 0 | $ 74 | $ 193 | |
Photovoltaic | Utility | 15% | 27% | $ 819 | $ 819 | $ 0 | $ 7 | $ 0 | $ 22 | $ 40 |
Commercial | 12% | 20% | $ 1,108 | $ 1,108 | $ 0 | $ 8 | $ 0 | $ 40 | $ 66 | |
Residential | 13% | 21% | $ 1,493 | $ 1,493 | $ 0 | $ 9 | $ 0 | $ 50 | $ 83 | |
Hydropower | 60% | 66% | $ 3,956 | $ 7,105 | $ 0 | $ 41 | $ 0 | $ 45 | $ 83 |
CF Range | CAPEX Range | OPEX | LCOE Range | |||||||
---|---|---|---|---|---|---|---|---|---|---|
Technology | Min. (%) | Max. (%) | Min. ($/kW) | Max. ($/kW) | Fuel Costs ($/MWh) | Fixed O&M ($/kW-yr) | Variable O&M ($/MWh) |
Min. ($/MWh) | Max. ($/MWh) |
|
Dispatchable | ||||||||||
Coal | PC | 53% | 85% | $ 3,527 | $ 3,896 | $ 19 | $ 33 | $ 5 | $ 74 | $ 105 |
IGCC | 53% | 85% | $ 3,524 | $ 4,180 | $ 19 | $ 54 | $ 8 | $ 84 | $ 118 | |
CCS-30% | 53% | 85% | $ 4,589 | $ 5,392 | $ 21 | $ 69 | $ 7 | $ 102 | $ 145 | |
CCS-90% | 53% | 85% | $ 5,074 | $ 5,962 | $ 25 | $ 80 | $ 10 | $ 117 | $ 166 | |
Natural Gas | CT | 8% | 30% | $ 783 | $ 783 | $ 28 | $ 12 | $ 7 | $ 59 | $ 122 |
CC | 56% | 87% | $ 923 | $ 923 | $ 19 | $ 10 | $ 3 | $ 30 | $ 36 | |
CC-CCS | 56% | 87% | $ 1,690 | $ 1,690 | $ 22 | $ 33 | $ 7 | $ 49 | $ 61 | |
Nuclear | 92% | 92% | $ 5,136 | $ 5,136 | $ 7 | $ 99 | $ 2 | $ 66 | $ 66 | |
Biopower | 56% | 56% | $ 3,385 | $ 3,714 | $ 39 | $ 51 | $ 5 | $ 112 | $ 113 | |
Geothermal | 80% | 90% | $ 4,667 | $12,445 | $ 0 | $ 145 | $ 317 | $ 80 | $ 230 | |
CSP with 10-hr TES | 44% | 60% | $ 4,627 | $ 4,627 | $ 0 | $ 50 | $ 4 | $ 73 | $ 99 | |
Non-Dispatchable | ||||||||||
Wind | Land-based | 20% | 55% | $ 1,215 | $ 2,281 | $ 0 | $ 39 | $ 0 | $ 27 | $ 124 |
Offshore | 34% | 54% | $ 2,062 | $ 5,091 | $ 0 | $ 122 | $ 0 | $ 60 | $ 152 | |
Photovoltaic | Utility | 15% | 27% | $ 667 | $ 667 | $ 0 | $ 6 | $ 0 | $ 18 | $ 32 |
Commercial | 12% | 20% | $ 952 | $ 952 | $ 0 | $ 7 | $ 0 | $ 34 | $ 56 | |
Residential | 13% | 21% | $ 1,140 | $ 1,140 | $ 0 | $ 7 | $ 0 | $ 38 | $ 62 | |
Hydropower | 60% | 66% | $ 3,956 | $ 6,749 | $ 0 | $ 41 | $ 0 | $ 45 | $ 79 |
Here, 2018 ATB cost and performance are summarized by technology for the year specified. CAPEX and LCOE are calculated based on current market conditions. Monetary values are in 2016$. Hydropower is classified as non-dispatchable because of operational constraints. Note that while the levelized cost of energy (LCOE) is provided as a summary metric, it is not the focus of this work.
The following figures illustrate CAPEX, capacity factor, and LCOE for the Base Year (2015), 2030, and 2050. The colored bars represent the range of characteristics for all representative plants included in the ATB. The black bars reflect representative ATB plant characteristics that align most closely with recently installed or anticipated near-term installations of electricity generation plants. For the renewable technologies, the ATB representative plants span the range of resource characteristics available within the contiguous United States. For fossil fuel technologies, the colored bars illustrate the effect of capacity factor assumptions.
The ATB plant characteristics (and associated resource quality) that most closely align with recently installed or anticipated near-term installations of electricity generation plants are as follows (see individual technology sections for description of ATB representative plant characteristics):
EIA (U.S. Energy Information Administration). 2018. Annual Energy Outlook 2018 with Projections to 2050. Washington, D.C.: U.S. Department of Energy. February 6, 2018. https://www.eia.gov/outlooks/aeo/pdf/AEO2018.pdf.